Edit a work order

  1. Go to Work orders;

  2. Click the work order you want to edit;
  3. Click Edit;
  4. Adjust the desired fields:
    1. Type — change the type of work;
    2. Status — change the status;
    3. Date, From and Until — reschedule the time window;
    4. Unit — choose a different unit or The whole property;
    5. Supplier — assign a different contractor or choose Nobody — still to be scheduled;
    6. Cost — enter or change the costs;
    7. Note — add or update a description.
  5. Click Save.

Leave the times empty to set the work order to the whole day. Leave the date empty to move the work order back to the To be scheduled list.